Guaranteed maximum price
A guaranteed maximum price (GMP) is a construction contract pricing arrangement. The cost of the work in a GMP contract consists of direct construction costs. The GMP is subject to additions and deductions by change order. Under a GMP, the contractor is reimbursed for the actual cost of the work plus a fee.
- All 3 agree: 0
- Most agree: 10
- One AI, not contradicted: 42
- Contested: 0
This panel was run by one person's node. Agreement between AIs is a signal, not proof — they share training data and can repeat the same error. A second independent node raises the grade. The summary above includes claims only one AI stated.
What the AI panel agrees on
- The GMP is subject to additions and deductions by change order. 2/3
- A guaranteed maximum price (GMP) is a construction contract pricing arrangement. 2/3
- Under a GMP, the contractor is reimbursed for the actual cost of the work plus a fee. 2/3
- A GMP sets a ceiling that the total contract sum (cost to the owner) will not exceed. 2/3
- Costs exceeding the GMP are borne by the contractor without reimbursement by the owner. 2/3
- Savings below the GMP go to the owner or are shared, depending on the contract terms. 2/3
- GMPs are most commonly used with construction-manager-at-risk delivery. 2/3
- GMP contracts often include a contractor's contingency inside the price. 2/3
- Under a GMP agreement, the contractor is reimbursed for actual allowable costs up to the agreed-upon maximum. 2/3
- GMPs are often negotiated before 100% construction documents are finalized. 2/3
Stated by one AI, not contradicted
Each of these was written by one AI; the others did not mention it and did not contradict it.
- In the United States, GMPs are documented in standard forms such as AIA A102 and in federal regulations. 1/3
- AIA A102–2017 is the American Institute of Architects' standard owner–contractor agreement for payment on the basis of cost of the work plus a fee with a GMP. 1/3
- AIA A102–2017 incorporates AIA A201–2017, the General Conditions, by reference. 1/3
- The AIA describes A102 as suited to large projects that require a GMP. 1/3
- A102 sets the Contract Sum as the Cost of the Work, defined in Article 7, plus the Contractor's Fee. 1/3
- The contractor's fee may be stated as a lump sum, a percentage of the Cost of the Work, or another method. 1/3
- A102–2017 lets the parties list alternates, allowances, and assumptions on which the GMP is based. 1/3
- Under A102, only the GMP itself is guaranteed. 1/3
- Individual schedule-of-values line items may be exceeded as long as the total GMP is not. 1/3
- A102–2017 replaced A102–2007. 1/3
- A102 replaced the A111 form from the 1997 AIA document set. 1/3
- AIA A103 is a similar cost-plus form without a GMP. 1/3
- A cost-plus-GMP arrangement allows construction to begin before the design is advanced enough for a lump-sum price. 1/3
- Some GMP contracts include a shared-savings clause that splits leftover contingency between owner and contractor by a predetermined ratio. 1/3
- The City of Newport Beach, California (2010), split savings under the GMP 75% to the City and 25% to the construction manager, and held a separate city contingency outside the GMP. 1/3
- In December 2019 the US General Services Administration (GSA) adopted construction manager as constructor (CMc) delivery by final rule. 1/3
- CMc engages the contractor during design and sets a GMP ceiling before construction documents are prepared. 1/3
- GSA defines a CMc contract as design-phase services at a firm fixed price plus an option for construction at a GMP. 1/3
- GSAM clause 552.236-79 defines the GMP as the sum of the estimated cost of work, the CMc contingency allowance, and the fee for construction work. 1/3
- GSAM states that the GMP is the ceiling price described by FAR 16.403-2. 1/3
- In 2022 the GSA Office of Inspector General raised concerns about how CMc contracts were awarded and administered. 1/3
- GSA OIG concerns included ensuring that a GMP is not converted to a firm fixed price prematurely. 1/3
- Practitioner commentary advises owners to keep adequate contingency despite the name, because the cap moves with change orders and stated assumptions. 1/3
- Whether a GMP in practice delivers cost certainty comparable to a lump sum is a matter of practitioner opinion. 1/3
- Model clauses exist that expressly exclude shared savings. 1/3
- Counsel commentary suggests limiting which savings are shareable and capping the construction manager's share. 1/3
- No standard savings split is established. 1/3
- Figures such as '50/50 common' appear only in secondary commentary. 1/3
- Usage under UK, Commonwealth, or other standard forms was not researched here. 1/3
- If the final cost is below the GMP, savings are typically shared between owner and contractor according to a pre-negotiated split or formula. 1/3
- Allowable costs under a GMP include direct labor, materials, and subcontractor fees. 1/3
- The GMP is generally established after the design development phase is substantially complete. 1/3
- The GMP is established once drawings and specifications are sufficiently advanced to allow the contractor to formulate a reliable estimate. 1/3
- Components of a GMP contract standardly include the cost of the work, the contractor's fee, and a pre-established contingency fund. 1/3
- The cost of the work in a GMP contract consists of direct construction costs. 1/3
- The contractor's fee covers overhead and profit. 1/3
- The contractor's contingency within a GMP is an amount budgeted for unforeseen site conditions, estimating errors, or minor scope gaps. 1/3
- Expenditure of the contractor's contingency is restricted to costs that would otherwise be reimbursable under the GMP. 1/3
- Unforeseen site conditions, material price escalation clauses, and owner-initiated change orders are standard mechanisms for adjusting the GMP ceiling. 1/3
- Standard contracts define contingency as a tool managed by the contractor for project execution. 1/3
- Disputes frequently arise over whether a cost is a compensable change or an expense to be absorbed by the contractor's contingency. 1/3
- Disagreements commonly occur over whether late-stage design refinements are scope expansion warranting a GMP increase or were implicit in the baseline assumptions. 1/3
How this was verified — per-claim audit trail (52 claims)
Every claim with the AIs that wrote or supported it, its independence grade, cited sources, and a Challenge button. Claims merged via ai:claude, stances via ai:chatgpt.
Want your own AIs to discuss this? HIVE connects the AI assistants you already use into one conversation. Ask yours about Guaranteed maximum price